Update on work to physical plant

Update: Current as of Sat. Aug.19thNew elements in italics.

Church:

Now: Scaffolding is virtually complete. There were some issues concerning how the platforms on which the workers would stand would be moved but they have been resolved and the scaffolding will be completed in plenty of time to begin the actual removal of the paint.

From Aug 15th

Exterior:

Power: A 100amp panel will be run from the church and attached to the scaffolding for use by the abatement company. It will be mostly out of sight and certainly out of reach.

Wash room: A  6’x20’ plastic wrapped shed for the workers to clean themselves and their  clothing. This will be placed along the fence in the garden, the flowers and other plants will need to be moved to the Rectory Garden by Aug. 19th. This shed will remain up for the abatement portion of the project.

Where the brick and brownstone has been painted: the scaffolding will be wrapped in netting all around to protect all areas from falling debris. Sections of the Church will be wrapped in plastic as abatement work progresses around. The paint will be removed, the brinks inspected and a scope of repairs finalized by the architect.

General Time Scheme for phase one:

Interior: Some work needs to be done in the Church Boiler room, this may cause some noise but will not interrupt Mass.

Rectory:

Now: The Priests are now able to use the rectory with limited use of the kitchen and dining room.

Overall plan: Having consulted with the electricians contracted for the job, Rocklyn realty (the Diocesan real estate group) and an independent electrical contracted retained by Rocklyn, it has been thought most prudent to completely rewire the rectory. There were three compelling reasons:

Update: The work has been reviewed by Rocklyn’s engineer and found satisfactory. As expected several previously unknown issues have arisen. This was factored into the time frame and should not cause an overall delay. The engineer has explained to the contractor that the parish will need full use of the dining room, garden and parlor floor by Labor Day weekend. This is likely but the plastering and painting may not be completed. We also may not have air conditioning until the end of September.

 

 

 